Item
|
Scope of Work
|
|
Topsoil Stripping and Stockpiling, and Grading |
-
Topsoil removal stockpiling screening and placement at final grade
-
Trucking surplus materials on and off-site
-
Swale construction
|
|
Artificial Sports Field Surfacing and Subdrainage Networks |
-
2 Football Fields with Field Turf Artificial Turf System on Field Turf Drainage Tile system c/w
-
Poly Liner Drainage layer and
-
Weeping tile system combined with Nilex Multi-Flow system
|
|
Site Fitments – Furnishings |
-
Benches, Picnic Tables, Tree Grates, Litter Containers, Bicycle Racks, T-Bollards c/w piles
|
|
Sports Fitments – Goals |
-
Football Goals, Soccer Goals, Elevated Bleachers, Players Benches, Timers Tables
|
|
Playground w/ Surfacing |
-
1000 sq. m. playground system with up to 10’ Fall Ht. c/w Poured in Place Rubber (full color) w/ CB drain weeping tile, concrete curb w/ colored chain link fencing and top cap.
|
|
GPS Survey and Layout |
-
Leica GPS equipment
-
CADD, Terra model, Pay Dirt software
|
|
Asphalt Paving |
-
Parking Lot Paving and Line Marking (8,500m2)
|
|
Concrete Forming |
-
Concrete Walks, Curbs, Gutters, Medians, Landscape Islands, Concrete Piles
|
|
Electrical Systems |
-
Musco Lighting Systems (9) – Galvanized poles c/w luminare supply and assembly (60’-70’ Ht.).
-
Musco Main distribution equipment
-
Nevco Scoreboard systems (2 @ approx. 28’length each) c/w distribution system and wireless remote
-
Allstar Show Industries Public Address System c/w wireless remote
|
|
Traffic Signage |
-
Stop Signs, Handi-Cap Stall Signs c/w piles
|
|
Aggregates - Install Base Courses |
-
Sports Field Granular Base (20,500m2)
-
Asphalt Paving Base (8,500 m2)
-
Field curbing and asphalt perimeter base work
|
|
Rough Grading |
-
Site Grading (95,000 m2)
-
Trucking surplus materials on and off-site
-
Swale construction
|
|
Segmental Retaining Walls |
-
Expocrete Block Wall (91m2 face) c/w geo-textile
|
|
Subgrade Preparation / Stabilization |
-
Subgrade Preparation over site c/w stabilization in areas as required (8,500m2)
|
Topsoil Stripping and Stockpiling,
and Grading
|
-
Topsoil removal stockpiling screening and placement at final grade (20,000 m2)
|
|
Mechanical Seeding / Sodding |
-
Seeding of Turf Areas or Sodding as required
|
|
Irrigation Systems |
-
Irrigation Systems for Artificial Fields c/w quick couplers
|
|
Water Park – Spray Decks |
-
Water Park and Spray Deck system installation
|
|
Fencing Systems and Gates |
-
4’ Chain Link Fencing and Gates
-
8’ Chain Link Fencing and Gates screened and not screened
|
|
Trees Shrubs and Ground Covers |
-
Mass planting installed as specified
|
|
Site Services- Distribution Piping, Fittings and Tie Ins |
-
Extensive underground service installation, water (580 lm), sanitary (185 lm), storm sewer (1,035 lm) connection tie into existing systems c/w base aggregates and compaction testing. Coordination and trenching for franchised utilities
|
|
Manholes Catch Basins |
-
Extensive Manholes and Catch Basin installations (25) with sanitary and storm services as required
|
|
CCTV Service Inspections |
-
CCTV Service Inspections on storm sewer and sanitary lines (1,220 lm)
|
|
Buildings and Structures |
-
Field House facilities ($2,500,000.00)
-
Change rooms
-
Office and lease spaces
-
Roof Top viewing deck and Concession Facilities
-
PA system, Lighting and Irrigation mechanical controls
|
|
Safety |
-
Maintaining a secure construction site in a public setting including public signage.
|